Skip to content

3.2.11 Primary Treatment Tanks

This section details the primary treatment tanks at the WWTP: Primary Tank 1 (PT-1), Primary Tank 2 (PT-2), and Pre-Anoxic Tank (AT-1), plus the alkalinity dosing system. Based on the LBC OWMS O&M Manual V1.1.

Overview

Primary treatment of raw wastewater is performed using existing septic tanks at the site plus 66,000 L of new primary treatment capacity at the WWTP. All tanks are installed below ground with waterproof lids and risers. They capture and process more than two-thirds of gross solids, grease, and oils. Desludging intervals are expected at approximately 6–8 years.

Primary and pre-anoxic treatment tanks diagram (PT-1, PT-2, AT-1)

Primary Tank 1 (PT-1)

Specifications

Item Detail
Capacity 22,000 L concrete tank
Coating Internal epoxy coating (H₂S attack prevention)
Manufacturer Taylex Tanks (Fastcall Plumbing NT)
Lids 2 × fibreglass lids and risers (Orenco)
Venting Venting lid with activated carbon odour suppression kit
Access Tank shield anti-access grate
Float Assembly MF4P-VC, 39" length (Orenco)

Function

Receives raw wastewater from the collection network (SPS1/SSP1 and SPS2/STEP tank). Treatment occurs via settling and anaerobic digestion. Can typically achieve BOD removal of >50% and TSS removal of >90% when using an effluent filter.

Operating Logic

Passive operation — no automated controls.

Primary Tank 2 (PT-2)

Specifications

Item Detail
Capacity 22,000 L concrete tank
Coating Internal epoxy coating (H₂S attack prevention)
Manufacturer Taylex Tanks (Fastcall Plumbing NT)
Lids 2 × fibreglass lids and risers (Orenco)
Effluent Filter Biotube Filter, 12" (FT1260-36, Orenco)
Access Tank shield anti-access grate

Function

Provides equalisation and stability by levelling out flow peaks and allowing consistent loading of the AdvanTex AX100 filters. Further primary treatment occurs before effluent exits via gravity through the effluent filter, retaining all solids and debris greater than 3 mm.

Operating Logic

Passive operation — primary treated effluent gravity flows from PT-1 into PT-2.

Pre-Anoxic Tank (AT-1)

Specifications

Item Detail
Capacity 22,000 L concrete tank
Manufacturer Taylex Tanks (Fastcall Plumbing NT)
Lids 2 × fibreglass lids and risers (Orenco)
Pump Package Orenco Biovault (PVU84-2425-L) with Biotube 24" cartridge
Discharge Pumps 2 × Orenco PF(50Hz)300534 — 1/2 hp, 30 gpm, 380 V 3Ø
Water Meter 50 mm HR MultiJet with 10 L pulse reed output (Thinkwater NT)

Function

Effluent gravity transfers from PT-2 into AT-1. A portion of treated effluent is pumped back from the AdvanTex Recirculation Tank, creating an anoxic environment for denitrification (conversion of NO₃ to N₂ gas by facultative heterotrophic bacteria).

Effluent is discharged to the downstream AdvanTex Recirculation Tank via duty/standby submersible pumps with float-controlled operation.

Operating Logic — Pre-Anoxic Pumps

Controls pumps (2), PF(50Hz)300534, 380 V 3Ø, 1/2 hp (1.1 A each) in duplex alternating, on-demand mode.

Float Operation:

Level Action
High Level Alarm / Lag Pump Enabled Lead Pump On
Mid level Pump(s) Off
Redundant Off / Low Level Alarm

Settings:

Parameter Value
High Level Delay 5.00 seconds
Lag Enable O/F
Minimum Run Time 30.00 seconds
Pump High Amp Alarm 4.10 A
Pump Low Amp Alarm 0.50 A
Pump 1 Liters per Minute 113.56 LPM
Pump 2 Liters per Minute 113.56 LPM

Alkalinity Dosing

Purpose

Nitrification in the AdvanTex system requires alkalinity to buffer the process (7.14 mg/L alkalinity per 1 mg/L ammonia-N). For complete nitrification, pH must remain between 7.5 and 8.5, always above pH 7 (nitrification ceases at pH 5).

Equipment

Item Detail
Chemical Sodium bicarbonate
Feed Unit Fiberglass Liquid Chem Feed Unit (LCF-C, Orenco) with internal mixer
Feed Pump Peristaltic alum feed pump (Orenco)
Target Residual Minimum 80 mg/L; preferred 100 mg/L

Sodium bicarbonate is dosed into the pre-anoxic tank upstream of the AdvanTex system. The Liquid Chem Feed Unit features an internal mixer to ensure adequate chemical mixing.

Operating Modes

Flow Pace (default): Peristaltic pump activation tied directly to pre-anoxic pump activation. Mixer activates prior to peristaltic pump (3 min pre-run default). Feed rate manually adjusted on peristaltic pump based on operator flow calculations.

Timer: Programmable ON/OFF times (factory default 1 min ON, 59 min OFF). Activated when LCFA RO float is up.

Maintenance

Task Action Frequency Responsible
Check Biotube® Effluent Filters (PT-2); clean as required Inspect 12" filter Quarterly ENVR
Visual inspection of liquid levels in all tanks Check all primary and anoxic tanks Quarterly ENVR
Sludge accumulation assessment Measure sludge and scum levels in Primary Tanks; organise de-sludge if required Quarterly ENVR
Inspect, test and clean all floats All tank float assemblies Quarterly ENVR
Inspect and clean intakes of all submersible pumps Pre-anoxic discharge pumps Annually ENVR

See 3.2.15 for the full maintenance program and contingency controls for declining TN/pH.

Version Control

Version Date Description
2.0 2026-06-22 Initial Release per O&M Manual V1.1
2.0.1 2026-06-22 Added primary and anoxic tanks diagram

Next Review Date: 2026-12-22