3.2.6 Gravity Mains

This section details the specifications for the sewer gravity mains and access chambers.

Zone 1 — Bungalows 17–59

  • Pipe: DN150 PVC gravity main running parallel to the access road, discharging to SPS1 (SSP1) septic tank
Chamber CCTV Location
Access Chamber 1 MH C Next to Bungalow / Unit 17
Access Chamber 2 MH A Behind Unit 40 (common area between Units 39 and 40); receives Zone 3 under-lake rising main from SSP3
Access Chamber 3 MH B Common area between Bungalows / Units 55 and 56

Access Chamber 2 (MH A) — Unit 40

Access pit behind Unit 40. The 40 mm lilac Zone 3 rising main from SSP3 lands here after crossing under the lake, then effluent continues in the DN150 gravity main toward SSP1. See 3.2.7 Rising Mains and 3.2.3 SSP3.

Access Chamber 1 (MH C) — Unit 17

Inside view of the Zone 1 gravity-main access pit next to Unit 17 (MH C / Access Chamber 1).

Zone 1 gravity main — Access Chamber 1 (MH C) next to Unit 17, looking in

Known Issues

  • Groundwater Ingress: Observed through joins in the access chamber nearest SSP1
  • Sealing: Gaps present between lids and riser pipes in both chambers
  • CCTV Priority 1 (6 March 2026): Pipe barrel structural grade 1. East-side Priority 1 repairs and the Unit 41 investigation are complete (Oct 2026) — see 5.2:

Programme summary remains on 5.1 East Side Septic Main Repair (status Complete).

Zone 2 — Bungalows 1–16

  • Pipe: Gravity sewer main to SPS2 (SSP2) STEP tank
  • Note: Previously fed a distribution box and septic tanks (now removed and replaced by the 22 kL STEP tank)

Zone 3 — Bungalows 65–66, 75–80

  • Pipe: Gravity sewer mains to SSP4 and SSP5 septic systems, then to SPS3 (SSP3) via 32 mm pipeline
Version Control
Version Date Description
1.0 2025-10-06 Initial Release
2.0 2026-06-22 Updated Zone 2 for STEP tank; added Zone 3 reference
2.1 2026-08-31 Linked 2026 gravity sewer main repair
2.2 2026-08-31 MH A–C labels and DHE CCTV Priority 1 defects
2.3 2026-10-25 Unit 41 branch repair complete; Priority 1 at 39/40 still open
2.4 2026-10-25 Unit 40 / MH A Repair 2 complete; only Unit 39 Repair 1 open
2.5 2026-10-25 Unit 39 Repair 1 complete; east-side Priority 1 programme closed
2.6 2026-10-26 Added MH C / Unit 17 access-chamber inside photo (moved from 3.2.1)
2.7 2026-10-26 Renamed MH C photo file; dropped SSP1-riser disclaimer
2.8 2026-10-30 MH A / Unit 40 noted as landing for SSP3 under-lake rising main

Next Review Date: 2027-04-26