Common-property green waste processing area on top of the hill, beside the potable water storage tanks. Owners may deliver garden / green waste here; Thursday kerbside green-waste pickup is on 6.1 Waste Collection.

Material must be sorted into the three piles below (left → right when facing the piles).

Green waste processing area — three sorted piles on the hill (2026-10-25)

Show on Map

Location

Item Detail
Site Top of the hill, near the water tank farm
Access Via the hill track / common-property access to the tank area
Nearby plant Potable storage tanks — 3.1.2 Storage Tanks; wood chipper WC-1 stored on site — 7.6 Wood Chipper
Map Placemark Green Waste Processing Area on the Interactive Map
Layout Three piles in a row (facing the piles: left, middle, right)

Sorting — Three Piles

Face the piles from the open hardstand. Sort every load into the correct pile. Each pile is processed differently.

Pile (facing piles) Put here End use
1 — Left Dirt, soft plants (mother-in-law’s tongue, birds of paradise, banana palms, and similar), and grass clippings Composted down to plant compost and topsoil
2 — Middle Hard wood and logs over 60 mm, large roots, and other material that will not go through the wood chipper Burnt, then turned into topsoil
3 — Right Palm fronds; branches under 60 mm; green palm stems under 60 mm; other chipper-suitable prunings Turned into wood chips

60 mm Rule

Under 60 mm (and soft enough / green palm stems) → right pile (wood chips). Over 60 mm, hard logs, and heavy roots → middle pile (burn → topsoil). Soft leafy / fleshy plants, grass clippings, and dirt → left pile (compost → plant compost and topsoil).

Pile 1 — Left (Compost / Topsoil)

  • Dirt and soft plant material
  • Grass clippings
  • Mother-in-law’s tongues, birds of paradise, banana palms, and similar
  • Outcome: composted down to plant compost and topsoil
  • Do not put hard logs or thick branches here

Pile 2 — Middle (Burn → Topsoil)

  • Hard wood and logs over 60 mm
  • Roots and other material that would not pass through the wood chipper
  • Outcome: burnt, then turned into topsoil
  • Keep chipper-sized green waste out of this pile

Pile 3 — Right (Wood Chips)

  • Palm fronds
  • Branches under 60 mm
  • Palm stems that are under 60 mm and still green
  • Other material intended for wood chipping
  • Outcome: processed into wood chips

What Is Accepted

Accepted Not accepted
Garden / green waste sorted into the three piles above General rubbish, household waste, or Coomalie wheelie-bin contents
Material owners bring themselves Building rubble, treated timber, metals, plastics (unless confirmed with the contractor)

Confirm borderline loads with Lakeside Upkeep and Tech (lakesideupkeepandtech@gmail.com) if unsure.

Who May Use It

Party Use
Owners Welcome to transport their own garden / green waste here — sorted into the correct pile
Caretaker / landscaping Lakeside Upkeep and Tech — holds the caretaker contract; processes / chips / removes material; Thursday kerbside green-waste pickup
Caretaker / Corporation agents Estate grounds work (clippings from mowing and similar)

Rules

  • Sort into the left / middle / right piles as above — do not leave unsorted heaps in front of the piles
  • Place green waste in the designated processing area only — not on roadsides, unit frontages, or beside the tanks themselves
  • Do not leave general rubbish here; Monday rubbish collection is Coomalie (240 L wheelie bin) — see 6.1
  • Do not obstruct tank farm access, manifolds, or fire / service vehicle routes
  • No dumping that risks runoff into stormwater or toward the lake — see 2.3.5 Environmental Management

Common Property

Leaving rubbish on common property outside these arrangements is prohibited — 2.3.3 Community Facilities.

Service Where
Thursday green-waste pickup 6.1 Waste Collection — Lakeside Upkeep and Tech
Monday rubbish (240 L) 6.1 Waste Collection — Coomalie Community Government Council
Grounds machines 7. Plant and Equipment
Wood chipper (WC-1) 7.6 Wood Chipper — Greenfield Piecemaker
Version Control
Version Date Description
1.0 2026-10-25 Initial Release — hill green-waste processing area (owner drop-off; map link)
1.1 2026-10-25 Photo; three-pile sort (soft/dirt; hard over 60 mm; chip under 60 mm)
1.2 2026-10-25 End uses: left compost/topsoil; middle burn→topsoil; right wood chips
1.3 2026-10-25 Grass clippings go on left pile
1.4 2026-10-28 Linked WC-1 Greenfield Piecemaker (7.6); stored on site