This page is the closed-out works register for Lake Bennett Estate common property: installations, upgrades, and repairs that have been finished and documented. It is the counterpart to 5.1 Planned Upgrades and Outages (needed / proposed / scheduled work).

As-built detail for plant that still exists belongs on the relevant page in sections 3 or 4. This register records what changed, when, who did it, and where the manual was updated — so history is not only in people’s heads or contractor email.

Living Register

When a job on 5.1 is marked Complete, add a row (and a short detail section if useful) here, then update the asset page. Do not leave finished work only on the planned register.

How to Record a Closed-Out Job

  1. Confirm the work is finished and services are restored
  2. Add a row to the Works Log below (newest first)
  3. Add a short detail section when contractors, isolations, or as-built changes matter later
  4. Update the asset page in section 3 or 4 (photos, specs, map placemark, Show on Map link)
  5. On 5.1, set status to Complete or remove the scheduled-outage row

What to Capture

Field Record
Date Practical completion (or date range if multi-day)
Type Installation / Upgrade / Repair
System Water, wastewater, power, roads, lighting, other
Asset Named plant or location (match the manual / map where possible)
Summary One or two sentences — what was done
Contractor Company and contact if known
As-built Link to the updated manual page (and map if the POI changed)
Evidence Photos, invoices, certificates, CCTV — note where they are kept

Lot-internal work belongs here only when it was authorised as common-property investigation or repair (same rule as 5.1).

Works Log

Date Type System Asset Summary As-built
2026-10-26 Upgrade Wastewater SSP1 / Pit 1 Removed two 5,000 L tanks; lift-well Gatic lid; site still has green power switch box (N.T. PIT-1) and white Pit 1 control panel 3.2.1 SSP1 Main Septic
2026-10-23 Repair Wastewater Unit 40 sewer / MH A Priority 1 mainline junction repair and Unit 40 connection at MH A (Repair 2) — new PVC tee, riser, and coupling 3.2.6 Gravity Mains
2026-10-22 Repair Wastewater Unit 41 sewer branch Replaced unit branch connection to the east-side 150 mm gravity main (Investigation 3 from the 2026 east-side programme) 3.2.6 Gravity Mains
2026-10-22 Repair Wastewater Unit 39 sewer / main Priority 1 mainline and Unit 39 connection repair (Repair 1) — excavated junction on A → C at 20.4 m from MH A 3.2.6 Gravity Mains

Add new rows at the top. Keep summaries short; put procedure and plant detail on the as-built page.

Detail Sections

2026-10-26 SSP1 / Pit 1 — Removal of Two 5,000 L Tanks

Item Detail
Type Upgrade (plant removal / decommission)
System Wastewater — Zone 1 collection (SSP1 / Pit 1)
Asset Two 5,000 L tanks at SSP1 / Pit 1; lift-well access lid
Completed 2026-10-26
Work done Removed both 5,000 L tanks and reinstated the ground. Lift-well lid changed from metal-handle style to a concrete cover with Gatic lifting slots. Remaining station plant: ~18,000 L primary septic, lift well, green power switch box (N.T. PIT-1 — breakers for Pit 1 and Pit 2), and white Pit 1 control panel
Access note Open the lift-well lid with a Gatic lifter only — do not use a crowbar (damages the concrete). Estate Plumboss lifter is stored in the WWTP control room. See 3.2.1 Access Lid
As-built 3.2.1 SSP1 Main Septic

SSP1 / Pit 1 after removal of two 5,000 L tanks — N.T. PIT-1 panel and remaining lids (2026-10-26)

SSP1 / Pit 1 lift-well lid — Gatic slots; open with Gatic lifter only (2026-10-26)

2026-10-23 Unit 40 Sewer Connection and Mainline Repair

Item Detail
Type Repair
System Wastewater — Zone 1 gravity sewer
Asset Communal 150 mm main at MH A (behind / in front of Unit 40) and Unit 40 connection — CCTV B → A at 0.8 m upstream of MH A
Completed 2026-10-23
Contractor Saunders Plumbing and Drainage (Joshua Saunders) — 0416 560 439 (pipe); excavation / locate as engaged for the east-side programme — see 5.1
Why CCTV (DHE, 6 March 2026) Priority 1: running infiltration (Grade 3) at an open 100 mm junction at 3 o'clock, 0.8 m upstream of MH A
Work done Excavated beside MH A; replaced the defective junction / connection with new PVC (tee, vertical inspection riser with cap); joined to the existing main with a stainless shielded coupling; removed failed / rusted metal pipe sections
As-built 3.2.6 Gravity Mains
Related planned works East-side Priority 1 programme (Repairs 1–2 and Investigation 3) is complete — see siblings below

Unit 40 sewer — mainline repair at MH A with stainless coupling and new riser (2026-10-23)

Unit 40 sewer — new PVC tee and capped inspection riser at Unit 40 connection (2026-10-23)

2026-10-22 Unit 41 Sewer Branch Repair

Item Detail
Type Repair
System Wastewater — Zone 1 gravity sewer
Asset Unit 41 private branch connection to the communal 150 mm main (CCTV B → A at 9.20 m from MH B)
Completed 2026-10-22
Contractor Saunders Plumbing and Drainage (Joshua Saunders) — 0416 560 439 (pipe); excavation / locate as engaged for the east-side programme — see 5.1
Why CCTV (DHE, 6 March 2026) showed water entering from the Unit 41 branch; junction on the main was intact — investigation confirmed a defective branch connection requiring replacement
Work done Excavated the branch beside the Unit 41 concrete edge; replaced the defective section with new PVC (elbows to align, vertical riser with inspection / vent cap); jointed and bedded before backfill
As-built 3.2.6 Gravity Mains
Related planned works East-side Priority 1 programme (Repairs 1–2 and Investigation 3) is complete — see siblings on this page

Unit 41 sewer branch — open trench showing existing pipe and coupling (2026-10-22)

Unit 41 sewer branch — new PVC run with elbows and capped riser before backfill (2026-10-22)

Unit 41 sewer branch — sand bedding over new pipe before reinstatement (2026-10-22)

2026-10-22 Unit 39 Sewer Connection and Mainline Repair

Item Detail
Type Repair
System Wastewater — Zone 1 gravity sewer
Asset Communal 150 mm main and Unit 39 connection in front of Unit 39 — CCTV A → C at 20.4 m from MH A
Completed 2026-10-22
Contractor Saunders Plumbing and Drainage (Joshua Saunders) — 0416 560 439 (pipe); excavation / locate as engaged for the east-side programme — see 5.1
Why CCTV (DHE, 6 March 2026) Priority 1: gushing infiltration (Grade 4) at 12 o'clock — failed joint or pipe section at 20.4 m from MH A
Work done Excavated in front of Unit 39 to the main; exposed and repaired the Unit 39 connection into the communal main (branch into horizontal main visible before backfill); groundwater present in the trench during works
As-built 3.2.6 Gravity Mains
Related planned works East-side Priority 1 programme (Repairs 1–2 and Investigation 3) is complete — see siblings on this page

Unit 39 sewer — excavation to main with standing water (2026-10-22)

Unit 39 sewer — Unit 39 branch into the communal main before backfill (2026-10-22)

Template (Copy for Each Job)

## YYYY-MM-DD — Short Title

| Item | Detail |
|:---|:---|
| **Type** | Installation / Upgrade / Repair |
| **System** | e.g. Wastewater |
| **Asset** | e.g. SSP4 / Pit 4 |
| **Completed** | YYYY-MM-DD (or range) |
| **Contractor** | Name — phone |
| **Isolation** | What was isolated; restore confirmed |
| **As-built** | Link to section 3 or 4 page |
| **Map** | Placemark updated / Show on Map checked |

Brief narrative: why the work was done, what was installed or replaced, and any operating change for caretakers or owners.

Relationship to Other Pages

Page Role
5.1 Planned Upgrades and Outages Forward-looking register and outage notices
Sections 3 and 4 Current as-built plant and roads
Interactive Map Location of plant after changes
1.4 Contact Information Committee and contractor contacts
Version Control
Version Date Description
1.0 2026-10-25 Initial Release — closed-out works register and recording template
1.1 2026-10-25 Unit 41 sewer branch repair (2026-10-22) with photos
1.2 2026-10-25 Unit 40 connection and mainline repair at MH A (2026-10-23) with photos
1.3 2026-10-25 Unit 39 connection and mainline repair (2026-10-22); east-side Priority 1 programme closed
1.4 2026-10-26 SSP1 / Pit 1 — two 5,000 L tanks removed; post-works photo
1.5 2026-10-26 SSP1 lift-well Gatic lid photo and crowbar warning
1.6 2026-10-26 SSP1 remaining plant wording — green power switch box vs white control panel

Next Review Date: 2027-04-26