5. Upgrades and Outages

This page is the working register of infrastructure and other estate work that needs doing, work that is proposed, what that work would interrupt, and scheduled outages. It is not a substitute for the as-built pages in sections 3 and 4.

Storm and network power failures are in 3.3.2 Backup Power. This page is for planned estate work only.

Living Register

Update this page when an item is identified, proposed, scheduled, or finished. As at 31 August 2026: east-side septic main repair targeted September 2026; SP4 procurement from late 2026; SP4 civil works may not start until late 2027.

How to Use This Page

Status Meaning
Needed Identified gap or plant that should be upgraded; not yet a committed project
Proposed Intended work; dates and outage window not locked
Scheduled Dates agreed; owners to be notified before the start
Complete Work finished; move the detail onto the relevant as-built page if plant changed

Recording a Scheduled Outage

  1. Confirm dates, isolation points, and affected services with the contractor
  2. Enter the work in Needed or Proposed Upgrades (or leave it there) and add a row under Scheduled Outages
  3. Notify owners via 1.4 Contact Information (lakebennettcommittee@gmail.com and Whittles notices) before the start time
  4. After restoration, mark the outage Complete and update the asset page if plant changed

Needed or Proposed Upgrades

Item System Need Status Outage Risk Detail
East-side septic main repair Wastewater Two Priority 1 groundwater infiltration repairs plus a Unit 41 branch investigation on the 150 mm gravity main Scheduled Sewer isolation up to one working day per stage; driveway closures at Units 39, 40, and 41 See below
SP4 replacement Wastewater Relocate and replace Pit 4 (Units 65–66) with a concrete tank, Orenco pumps, and bar screen Scheduled (buy late 2026; civil late 2027) Cutover outage for Units 65 and 66 only, when install proceeds See below
DB1 generator changeover procedure Power Written checklist for connect, changeover, WWTP post-checks, and return to mains is not yet published Needed None (documentation). Live generator work would follow 3.3.2 Backup Power 3.3.2 Backup Power
Recycled water reuse Wastewater Class A water in the RWS tanks is intended for a future community nursery and estate greening Proposed Isolation of RWS or LAA only if pipework is altered; not scheduled 3.2.14 Recycled Water Storage
As-constructed drawings pack Records Survey / as-constructed drawings still to be collected Needed None 2.4 Easements

Add further rows as plant, roads, or other common-property work is identified. Do not record lot-internal upgrades here except where a communal investigation assigns owner-side work.

East Side Septic Main Repair (2026)

Priority 1 repairs and a targeted junction investigation on the east-side communal 150 mm PVC gravity sewer (Zone 1 — 3.2.6 Gravity Mains). Structural condition of the pipe barrel is sound (structural grade 1). CCTV survey by DHE, 6 March 2026 (WSA 2020).

Item Detail
Asset Communal gravity sewer (sewage only), easement at Unit 40
Pipe 150 mm circular PVC
Inspected length 288.30 m (three sections)
Manholes MH A behind Unit 40; MH B between Units 55 and 56; MH C next to Unit 17
Target start September 2026 (indicative; mid to end of dry season)
Do not schedule Wet season, school holidays, public holidays
Working hours 08:00–17:00 Monday–Friday (to be confirmed with contractors)
Physical works About 5–9 working days (two repairs, one investigation, driveway make-good and cure)
Programme About 4–5 weeks from committee approval to close-out
Status Scheduled (exact start TBC once contractors are engaged and owner notices issued)

In Scope

Work Section Chainage Unit What
Repair 1 A → C 20.4 m from MH A 39 Gushing infiltration at 12 o'clock (Grade 4) — replace failed joint or pipe section
Repair 2 B → A 0.8 m upstream of MH A 40 Running infiltration at 3 o'clock at an open 100 mm junction (Grade 3) — reseal or replace saddle
Investigation 3 B → A 9.20 m from MH B 41 Water entering from the unit branch; junction intact on CCTV — confirm source and whether body corporate or lot-owner repair

Investigation 3 does not include private plumbing unless the findings show a communal defect and the committee authorises remedial work.

Out of Scope

Priority 2–4 CCTV items (ponding, pipe indent, grease, seepage, surface damage, and systemic open-junction remediation) are not in this project. No full main replacement, no jet-clean of the 288 m network, and no post-repair CCTV.

Contractors

Role Party Contact
Coordination, concrete cut, driveway make-good Harrison Homes & Renovations Pty Ltd 0447 719 071
Licensed plumber Saunders Plumbing and Drainage (Joshua Saunders) 0416 560 439
Excavation and backfill Dash Excavations Engaged by the committee
Service locate Austar Underground Services 0402 503 073 / 0412 751 552
CCTV (complete) DHE (Dig Hard Excavations) Survey 6 March 2026 on file
Owner liaison Whittles on behalf of the committee Units 39, 40, and 41
Notices and complaints Lake Bennett Body Corporate Committee lakebennettcommittee@gmail.com

Sequence at each work zone: Austar locate → Harrison saw-cut driveway → Dash trench → Saunders sewer works → Dash backfill → Harrison driveway make-good → cure → reopen.

Interruptions

Impact Detail
Sewer use Isolation (plug, over-pump, or vacuum tanker) — no more than one working day per stage, subject to what is found when the pipe is opened
Driveways Units 39, 40, and 41 — no vehicle access while slabs are cut, trenches are open, and until new concrete is trafficable (tentatively 48 hours after pour; Harrison to confirm)
Access Unit 40 easement unrestricted; works under owners' concrete driveways
Environment No sewage or dewatering to ground, stormwater, or the lake catchment; vacuum tanker on standby; 100 m lake setback applies

Lake Catchment

No raw sewage or dewatering discharge within 100 m of lake full supply level. See 2.3.5 Environmental Management.

Owner Notices

Minimum 7 days before Notices 2 and 3. Audience for Notice 1 is all east-side owners Units 39–58. Whittles contacts driveway owners at Units 39, 40, and 41.

Notice When
1 — Intent Within 7 days of committee approval
2 — Pre-works Minimum 7 days before first excavation
3 — Stage update Minimum 7 days before each of Repair 1, Repair 2, and Investigation 3
4 — Completion Within 7 days of final reinstatement

Include in notices: reduce non-essential water use; no fats, oils, or grease; keep children and pets away from open excavations; report surfacing effluent to the committee.

SP4 Replacement (Pit 4)

Replace the existing Sewage Pit 4 (3.2.4 SSP4 Everhard) with a new concrete tank, Orenco pumps and controls, and a bar screen. Relocate onto common land, further from the lake high-water line. New rising main to 3.2.3 SSP3. Serves Units 65 and 66 only.

Drivers: flat invert causing sludge and blockages; pump clogging from wet wipes; flood risk at the current foreshore site. Orenco equipment is specified for interchangeability with the rest of the estate OWMS.

Item Detail
Current plant Everhard 3,000 L plastic septic and polymer lift well between Units 65 and 66
New plant 5,000 L concrete tank (baffle, two access openings); Orenco duplex pumps and panel; Biotube / bar screen
Power Existing circuit and subsurface wiring from the west-side main switchboard (DSB-DB1) to a new control board beside the new pit
Crane / delivery Tilt-tray via Chinner Road onto common land; crane stages beside the excavation (no private-lot easement)
Procurement Starts late 2026 (equipment and parts — tank, Orenco kit via ENVR)
Civil and install May not start until late 2027; tank lift preferred in the dry season when ground is firm
Cutover Agreed outage window for Units 65 and 66 only; then pump-out and make-safe of the old pit
Status Scheduled for procurement; civil dates indicative

In Scope

  • Survey, setbacks, and layout (Earl James; AWS)
  • Hydraulic design, Section 40, and BAS plumbing-only notifications (Tier 1 building control area)
  • Procurement of tank, Orenco pumps, controls, and bar screen (ENVR)
  • Excavation, rising main to SPS 3, crane set, plumbing, and electrical
  • Commissioning, cutover, old-pit pump-out and decommissioning, as-builts and O&M handover

Out of Scope

Upgrades to SPS 3 beyond the new rising-main connection; upstream pipework from Units 65 and 66 unless design finds it must be repaired; other estate pits; landscaping beyond safe access.

Timing

Phase Target Outage
1–2 Survey, design, approvals Before equipment order None
3 Procurement From late 2026 — order tank and Orenco parts (lead time is on the critical path) None
4–5 Civil, install, cutover May not start until late 2027 Units 65 and 66 — agreed window at cutover only

Do not set the tank in saturated ground. Align crane, tilt-tray, and excavation on one day.

Contractors

Role Party
Equipment (tank, Orenco, bar screen) ENVR Solutions (Matt McKennariey) — 0402 524 033
Hydraulic design and as-builts Architectural Water Solutions (AWS)
Survey Earl James and Associates
Excavation Dash Excavations
Plumber / certification Saunders Plumbing and Drainage — 0416 560 439
Electrical Top End Electrical — 08 8945 5684 (west-side DB feed)
Crane Territory Crane Services
Old-pit pump-out Ecotreat Solutions NT

Committee approvals: approach and location; budget after design; cutover date and notice to Units 65 and 66.

Interruptions

Impact Detail
Sewer (Units 65 and 66) Existing SP4 stays in service until cutover. Outage only for the agreed cutover window — notify those two units in advance
SPS 3 / east side No intended interruption beyond connecting the new rising main
West-side power Brief work at DSB-DB1 / existing SP4 feed when the new control board is connected
Chinner Road / common land Tank delivery and crane on install day

Lake Catchment

New SP4 must sit at least 100 m from lake full supply level (or outside the catchment). No effluent to the lake. See 2.3.5 Environmental Management.

Potential Outages

Typical interruptions if the matching plant is isolated for upgrade or repair. Actual duration depends on the job.

Work on Typical interruption What still runs Contingency
Potable isolation (central box, Unit #17, western easement, WWTP green box) Water to the isolated units or to the control room Other zones if isolation is segmental; hill tanks still feed open legs 3.1.4 Reticulation
Bores or chlorine dosing No tank refill; no dosing while isolated Gravity supply from hill tanks 3.1 Water Supply, 3.3.2 Backup Power
WWTP or control room Treatment, LAA irrigation, and RWS fill Collection pits until they back up; RWS as wet-weather buffer 3.2.15 O&M and Contingency
East-side gravity sewer (2026 project) Restricted sewer use up to one working day per stage; driveway closures at Units 39–41 Other collection zones; WWTP if flow is still delivered Vacuum tanker; over-pump at MH A
SP4 replacement (late 2027 civil) Agreed cutover outage for Units 65 and 66 only All other collection zones; existing SP4 until cutover Notify 65 and 66; plumber on site; then pump-out old pit
Sewage pump stations That collection zone stops lifting Upstream gravity until pits fill Pit 1 and Pit 2 typically need power within about 12 hours
Grid / DB1 Estate infrastructure power Gravity water until tanks draw down Hire generator at DB1 — 3.3.2 Backup Power
Internal roads Vehicle access on the closed section Other estate roads if not blocked 4.4 Emergency Access

Sewer Backup Window

Planned electrical or WWTP outages that last toward 12 hours need a hire generator at DB1, or pump-out, before Pit 1 and Pit 2 back up. See 3.3.2 Backup Power and 3.2.9 Reservoir Impact.

Scheduled Outages

Start End Service Area Reason Status
September 2026 (indicative) About 4–5 weeks from start Gravity sewer East side Units 39–58; driveways 39, 40, 41 Priority 1 infiltration repairs and Unit 41 junction investigation Scheduled
Late 2026 Procurement only SP4 equipment (no service outage) Order concrete tank and Orenco pumps, controls, and bar screen Scheduled
Late 2027 (indicative) TBC at cutover SSP4 Units 65 and 66 Civil install, rising main to SPS 3, cutover, decommission old pit Proposed

Exact start is confirmed when contractors are engaged and Notice 2 is issued. Do not leave stale dates after close-out.

Notices

Item Detail
Who sends Estate committee
Channels lakebennettcommittee@gmail.com; Whittles owner portal notices; letterbox / noticeboard for east-side sewer works
What to include Start and end, service affected, area (units or plant), isolation points, who to call

Contacts: 1.4 Contact Information.

Version Control

Version Date Description
1.0 2026-08-31 Initial Release
1.1 2026-08-31 Gravity sewer main repair scheduled for 2026 (dates TBC)
1.2 2026-08-31 East-side septic main repair from project scope (Priority 1, September 2026)
1.3 2026-08-31 SP4 replacement — procure late 2026; civil may wait until late 2027

Next Review Date: 2027-02-28